File #: 16-00963    Version: 1
Type: Agenda Item Status: Passed
File created: In control: BOARD OF SUPERVISORS
On agenda: 12/13/2016 Final action: 12/13/2016
Title: Consider recommendations regarding the Transition Structure Portion of the Las Vegas and San Pedro Creeks Capacity Improvement Project, Second District, as follows: Acting as the Board of Directors, Flood Control and Water Conservation District: a) Approve and authorize the Chair to execute the Statement of Final Quantities for work performed and materials supplied for the Transition Structure portion of the Las Vegas and San Pedro Creeks Capacity Improvement Project by the contractor Souza Construction, Inc. (a tri-county vendor), in the amount of $683,235.48; and b) Determine, pursuant to 14 California Code of Regulations 15162, that no substantial changes are proposed in the project, no substantial changes have occurred with respect to the circumstances under which the project is undertaken, and now new information of substantial importance has been received with respect to the project of the mitigation measures, and therefore the recommended actions are within the scope of the M...
Sponsors: PUBLIC WORKS DEPARTMENT, BOARD OF DIRECTORS, FLOOD CONTROL AND WATER CONSER
Attachments: 1. Board Letter, 2. Attachment A Statement of Final Quantities, 3. Attachment B Project Element Map

Title

 

Consider recommendations regarding the Transition Structure Portion of the Las Vegas and San Pedro Creeks Capacity Improvement Project, Second District, as follows:

 

Acting as the Board of Directors, Flood Control and Water Conservation District:

 

a) Approve and authorize the Chair to execute the Statement of Final Quantities for work performed and materials supplied for the Transition Structure portion of the Las Vegas and San Pedro Creeks Capacity Improvement Project by the contractor Souza Construction, Inc. (a tri-county vendor), in the amount of $683,235.48; and

 

b) Determine, pursuant to 14 California Code of Regulations 15162, that no substantial changes are proposed in the project, no substantial changes have occurred with respect to the circumstances under which the project is undertaken, and now new information of substantial importance has been received with respect to the project of the mitigation measures, and therefore the recommended actions are within the scope of the Mitigated Negative Declaration adopted for the Las Vegas-San Pedro Capacity Improvement Project on October 4, 2011 and Addendums 1, 2, and 3 to the Mitigated Negative Declaration approved on April 10, 2012, August 19, 2014, and July 7, 2015, respectively, and that no subsequent Environmental Impact Report or Negative Declaration is required for the approval of the recommended actions.