File #: 23-00890    Version: 1
Type: Departmental Agenda Status: Agenda Ready
File created: 9/7/2023 In control: BOARD OF SUPERVISORS
On agenda: 9/19/2023 Final action: 9/19/2023
Title: HEARING - Consider recommendations regarding an appeal of the Planning Commission's approval of the Change of Ownership, Change of Guarantor, and Change of Operator for the Las Flores Pipeline System (formerly Plains All American Lines 901/903), First, Third, and Fourth Districts, as follows: (EST. TIME: 1 HR. 30 MIN.) a) Deny the appeal, Case No. 23APL-00027; b) Make the required findings for approval for the Change of Ownership, Change of Guarantor, and Change of Operator, including California Environmental Quality Act (CEQA) findings; c) Determine the request is not a project pursuant to CEQA Guidelines Section 15378(b)(5); and d) Grant de novo approval of the Change of Ownership, Change of Guarantor, and Change of Operator for Final Development Plan Permit No. 88-DPF-033 (RV01)z, 88-CP-60 (RV01)(88-DPF-25cz; 85-DP-66cz; 83-DP-25cz), subject to the Conditions of Approval. COUNTY EXECUTIVE OFFICER'S RECOMMENDATION: POLICY
Sponsors: PLANNING AND DEVELOPMENT DEPARTMENT
Attachments: 1. Board Letter, 2. Attachment A - Findings, 3. Attachment B - COAs Las Flores Pipeline, 4. Attachment C - CEQA NOE, 5. Public Comment - Group 1, 6. Public Comment - Law Office of Marc Chytilo, APC, 7. Public Comment - Cooke, 8. Public Comment - WE Watch, 9. Appellant Letter, 10. Applicant - Board Response letter dated 9-15-2023, 11. Presentation - Appellant, 12. Presentation - Applicant, 13. Presentation - Staff, 14. Presentation - Appellant Replacement 1, 15. Public Comment Speaker, 16. Minute Orders
Related files: 23-00814

Title

HEARING - Consider recommendations regarding an appeal of the Planning Commission’s approval of the Change of Ownership, Change of Guarantor, and Change of Operator for the Las Flores Pipeline System (formerly Plains All American Lines 901/903), First, Third, and Fourth Districts, as follows: (EST. TIME: 1 HR. 30 MIN.)

 

a) Deny the appeal, Case No. 23APL-00027;

 

b) Make the required findings for approval for the Change of Ownership, Change of Guarantor, and Change of Operator, including California Environmental Quality Act (CEQA) findings;

 

c) Determine the request is not a project pursuant to CEQA Guidelines Section 15378(b)(5); and

 

d) Grant de novo approval of the Change of Ownership, Change of Guarantor, and Change of Operator for Final Development Plan Permit No. 88-DPF-033 (RV01)z, 88-CP-60 (RV01)(88-DPF-25cz; 85-DP-66cz; 83-DP-25cz), subject to the Conditions of Approval.

 

COUNTY EXECUTIVE OFFICER’S RECOMMENDATION: POLICY