Title
Consider recommendations regarding the Goleta Beach Sand Replenishment Project, Project No. 8598, Second District, as follows:
a) Approve and authorize the Chair to execute a Contract with Penfield and Smith (a local consultant) for construction services management of the Goleta Beach Sand Replenishment Project in the amount of $185,308.00;
b) Approve the plans and specifications for the construction of Goleta Beach Sand Replenishment, Project No. 8598;
c) Award AIS of Carpinteria (a local vendor), the lowest responsible bidder, the construction contract in the amount of $1,578,000.00 subject to the provisions of documents and certifications as set forth in the plans and specifications applicable to the project, as required under California Law; and
d) Approve and authorize the Chair to execute the Construction Contract upon return of the contractor's executed contract documents, and the review and approval of the County Counsel, Auditor-Controller and Risk Manager or their authorized representatives.