File #: 14-00709    Version: 1
Type: Agenda Item Status: Passed
File created: 8/28/2014 In control: BOARD OF SUPERVISORS
On agenda: 9/9/2014 Final action: 9/9/2014
Title: Acting as the Board of Directors, Flood Control and Water Conservation District: Consider recommendations regarding the Local Sponsor Cost Sharing Agreement, Lower Mission Creek Flood Control Project, Second District, as follows: a) Approve and authorize the Chair to execute the Local Sponsor Cost Sharing Agreement for the construction of Reach 1A-2 of the Lower Mission Creek Flood Control Project in an estimated amount of $1,181,795.75 as a part of the Mason Street Bridge Replacement Project; b) Approve plans and specifications for the Lower Mission Creek Flood Control Project Reach 1A - Phase 2; and c) Find that pursuant to the California Environmental Quality Act (CEQA) Guidelines section 15162, no substantial changes are proposed, there are no substantial changes in circumstances and no new information of substantial importance has come to light regarding environmental effects of the project or feasibility of mitigation measures and, therefore this action is within the...
Sponsors: PUBLIC WORKS DEPARTMENT, BOARD OF DIRECTORS, FLOOD CONTROL AND WATER CONSER
Attachments: 1. Board Letter, 2. Contract Summary, 3. Agreement, 4. Plans, 5. Specs
Title
 
Acting as the Board of Directors, Flood Control and Water Conservation District:
 
Consider recommendations regarding the Local Sponsor Cost Sharing Agreement, Lower Mission Creek Flood Control Project, Second District, as follows:
 
a) Approve and authorize the Chair to execute the Local Sponsor Cost Sharing Agreement for the construction of Reach 1A-2 of the Lower Mission Creek Flood Control Project in an estimated amount of $1,181,795.75 as a part of the Mason Street Bridge Replacement Project;
 
b) Approve plans and specifications for the Lower Mission Creek Flood Control Project Reach 1A - Phase 2; and
 
c) Find that pursuant to the California Environmental Quality Act (CEQA) Guidelines section 15162, no substantial changes are proposed, there are no substantial changes in circumstances and no new information of substantial importance has come to light regarding environmental effects of the project or feasibility of mitigation measures and, therefore this action is within the scope of the project covered by the Environmental Impact Report/Environmental Impact Statement (EIR/EIS) for the Lower Mission Creek Flood Control Project as well as the Findings, and Statement of Overriding Considerations approved and adopted by the Board on May 10, 2011, and therefore, no subsequent environmental document is required.