File #: 18-00672    Version: 1
Type: Agenda Item Status: Passed
File created: In control: BOARD OF SUPERVISORS
On agenda: 8/28/2018 Final action: 8/28/2018
Title: Consider recommendations regarding a Statement of Final Quantities for the construction of Ray Road Rehabilitation, Project No. 820714, Third District, as follows: a) Approve and authorize the Chair to execute a Statement of Final Quantities for the Construction of Ray Road Rehabilitation for work performed and materials supplied by CalPortland Construction, Inc., (a local vendor), 1625 East Donovan Road, Santa Maria, CA 93454, in the amount of $387,199.80; and b) Determine the project was found by your Board to be exempt from the provisions of the California Environmental Quality Act pursuant to 14 CCR 15301(c) on July 25, 2017 (as the proposed project(s) consists of the operation, repair, maintenance, or minor alteration of existing public or private structures, facilities, mechanical equipment, or topographical features, involving negligible or no expansion of use beyond that previously existing, including but not limited to existing highways and streets, sidewalks, gutters, bicyc...
Sponsors: PUBLIC WORKS DEPARTMENT
Attachments: 1. Board Letter, 2. 820714 SFQ signed thru Scott, 3. ATT B_NOE Signed RoadMap 17-18

Title

Consider recommendations regarding a Statement of Final Quantities for the construction of Ray Road Rehabilitation, Project No. 820714, Third District, as follows:

 

a) Approve and authorize the Chair to execute a Statement of Final Quantities for the Construction of Ray Road Rehabilitation for work performed and materials supplied by CalPortland Construction, Inc., (a local vendor), 1625 East Donovan Road, Santa Maria, CA 93454, in the amount of $387,199.80; and

 

b) Determine the project was found by your Board to be exempt from the provisions of the California Environmental Quality Act pursuant to 14 CCR 15301(c) on July 25, 2017 (as the proposed project(s) consists of the operation, repair, maintenance, or minor alteration of existing public or private structures, facilities, mechanical equipment, or topographical features, involving negligible or no expansion of use beyond that previously existing, including but not limited to existing highways and streets, sidewalks, gutters, bicycle and pedestrian trails, and similar facilities), a Notice of Exemption was filed on that basis, and the proposed action is within the scope of the Notice of Exemption.